Completion Date | 2018 |
TOFCO Scope | Mechanical, Piping, Structural , Installation & Electrical and Instrumentation |
Location | Onshore/Offshore |
Type | NUI, Gas Production Facility |
Overall Tonnage | 188 |
Completion Status | Commissioned and leak tested prior to loadout |
Duration (months) | 8 |
Maximum Resource | 36 |
Manhours | 46427 |
Schedule Performance | On time |
Incident Rate | 0.62 |