Completion Date | 2017 |
TOFCO Scope | Mechanical, Piping and Structural |
Location | Onshore |
Type | Gas Production Facility |
Overall Tonnage | 194 |
Completion Status | Commissioned and leak tested prior to loadout |
Duration (months) | 24 |
Maximum Resource | 37 |
Manhours | 47990 |
Schedule Performance | On time |
Incident Rate | 0 |