| Completion Date | 2017 |
| TOFCO Scope | Mechanical, Piping and Structural |
| Location | Onshore |
| Type | Gas Production Facility |
| Overall Tonnage | 194 |
| Completion Status | Commissioned and leak tested prior to loadout |
| Duration (months) | 24 |
| Maximum Resource | 37 |
| Manhours | 47990 |
| Schedule Performance | On time |
| Incident Rate | 0 |