| Completion Date | 2018 |
| TOFCO Scope | Mechanical, Piping, Structural and Installation |
| Location | Onshore/Offshore |
| Type | Gas Production Facility |
| Overall Tonnage | 392 |
| Completion Status | Commissioned and leak tested prior to loadout |
| Duration (months) | 12 |
| Maximum Resource | 67 |
| Manhours | 96710 |
| Schedule Performance | On time |
| Incident Rate | 0.62 |