BpTT/MDR – Angelin Offshore Hookup & Start Up Stay Up (SUSU)
Completion Date2018
TOFCO ScopeSupport Brownfield Hookup and Commissioning
LocationOnshore/Offshore
TypeNUI, Gas Production Facility
Overall Tonnage226
Completion StatusCommissioned and leak tested prior to loadout
Duration (months)15
Maximum Resource44
Manhours55862
Schedule PerformanceOn time
Incident Rate0.62