BGTT Poinsettia
Completion DateFebruary 2010
Work ScopeDeck Fabrication, Offshore hookup
Duration18 Months
Overall Tonnage4,300 tons
Deck Weight3,648 tons
Max Resources300

› Extensive participation in engineering phase

› Offshore hook up by TOFCO

› It took 96 crew members 35 days to hook up this topside deck

› Successfully reached mechanical completion without injury, before target date, under budget

› Recipient of 2009 Overseas Project of the Year Award from the UK-based Association of Project Management (APM)

› BG presented TOFCO with the President’s HSSE Recognition Award for TOFCO’s contribution to HSSE for Safety Step-up